NHS Connecting for Health is part of the UK Department of Health and was formed on 1 April 2005, replacing the former NHS Information Authority. It has the responsibility of delivering the NHS National Programme for IT (NPfIT), an initiative by the Department of Health in England to move the National Health Service (NHS) in England towards a single, centrally-mandated electronic care record for patients and to connect 30,000 General practitioners to 300 hospitals, providing secure and audited access to these records by authorised health professionals.
In due course it is planned that patients will also have access to their records online through a service called HealthSpace. NPfIT is said by NHS CFH to be "the world's biggest civil information technology programme".[1]
The cost of the programme, together with its ongoing problems of management and the withdrawal or sacking of two of the four IT providers, have placed it at the centre of ongoing controversy, and the Commons Public Accounts Committee has repeatedly expressed serious concerns over its scope, planning, budgeting, and practical value to patients[2][3][4]. As of January 2009, while some systems were being deployed across the NHS, other key components of the system were estimated to be four years behind schedule, and others had yet to be deployed outside individual trusts at all[4].
While the Daily Mail announced on 22nd September 2011 that "£12bn NHS computer system is scrapped...",[5] The Guardian noted that the announcement from the Department of Health on 9th September,[6] had been "part of a process towards localising NHS IT that has been under way for several years".[7] Whilst remaining aspects of the National Programme for IT were cancelled, most of the spending would proceed with the Department of Health seeking for local software solutions rather than a single nationally imposed system.[8]
Contents |
The programme was established in October 2002 following several Department of Health reports on IT Strategies for the NHS.[9], and on April 1, 2005 a new agency called NHS Connecting for Health (CfH) was formed to deliver the programme. CfH absorbed both staff and workstreams from the abolished NHS Information Authority, the organisation it replaced. CfH is based in Leeds, West Yorkshire.
As of 2009, it is still managed nationally by CfH, with responsibility for delivery shared with the chief executives of the ten NHS strategic health authorities[4].
The refusal of the DoH to make "concrete, objective information about NPfIT's progress [...]available to external observers", nor even to MPs, has attracted significant criticism, and was one of the issues which in April 2006 prompted 23 academics[10] in computer-related fields to raise concerns about the programme in an open letter to the Health Select Committee.[11][12] 2006-10-06 the same signatories wrote a second open letter[13]
A report by the King's Fund in 2007 also criticised the government's "apparent reluctance to audit and evaluate the programme", questioning their failure to develop an ICT strategy whose benefits are likely to outweigh costs and the poor evidence base for key technologies[14].
A report by the Public Accounts Committee in 2009 called the risks to the successful deployment of the system "as serious as ever", adding that key deliverables at the heart of the project were "way off the pace", noting that "even the revised completion date of 2014-2015 for these systems now looks doubtful in the light of the termination last year of Fujitsu's contract covering the South", and concluding "essential systems are late, or, when deployed, do not meet expectations of clinical staff"[15].
The initial reports into the feasibility of the scheme, known to have been conducted by McKinsey, and subsequent reports by IT industry analyst Ovum among others[16] have never been published nor made available to MPs[17].
Originally expected to cost £2.3 billion (bn) over three years, in June 2006 the total cost was estimated by the National Audit Office to be £12.4bn over 10 years, and the NAO also noted that "...it was not demonstrated that the financial value of the benefits exceeds the cost of the Programme"[18]. Similarly, the British Computer Society (2006) concluded that "...the central costs incurred by NHS are such that, so far, the value for money from services deployed is poor"[19]. Officials involved in the programme have been quoted in the media estimating the final cost to be as high as £20bn, indicating a cost overrun of 440% to 770%[20].
In April 2007, the Public Accounts Committee of the House of Commons issued a damning 175-page report on the programme. The Committee chairman, Edward Leigh, claimed "This is the biggest IT project in the world and it is turning into the biggest disaster." The report concluded that, despite a probable expenditure of 20 billion pounds "at the present rate of progress it is unlikely that significant clinical benefits will be delivered by the end of the contract period."[2]
The costs of the venture should have been lessened by the contracts signed by the IT providers making them liable for huge sums of money if they withdrew from the project; however, when Accenture withdrew in September 2006, then Director-General for NPfIT Richard Granger charged them not £1bn, as the contract permitted, but just £63m[21]. Granger's first job was with Andersen Consulting[22], which later became Accenture.
The programme is divided into a number of key deliverables.
Deliverable | Since | Name of software | Original delivery date | Progress 2007[14] | Progress 2009[4] |
Integrated care records service | 2002 | NHS Care Records Service (NCRS) / Lorenzo | 2004 | "Real progress only just beginning", no go-live date specified | "Recent progress...very disappointing", completion date of 2014-2015 now looks unlikely following withdrawal of Fujitsu, arrangements for South region not resolved, Lorenzo still not live in a single acute Trust |
Electronic prescribing | 2002 | NHS Electronic Prescription Service | 2007 | Implementation began in early 2005, used for 8% of daily prescriptions | 70% of GPs and pharmacies had 1st release of software, but only 40% of prescriptions issued with readable barcodes |
Electronic appointments booking | 2002 | Choose and Book | 2005 | Take-up slow, system reliant on outdated technology, GPs dissatisfied, target of 90% of referrals on system by March 2007 missed | Mixed, around half of new appointments made using system, additional training and time required |
Underpinning IT infrastructure | 2002 | New National Network (N3) | March 2002 | On schedule, with 98% of GP practices connected | |
Medical imaging software | Picture Archiving and Communication System (PACS) | ||||
Performance management of primary care | Quality Management and Analysis System (QMAS) | ||||
Central e-mail and directory service | NHSmail* |
*NHSmail was renamed to Contact in late 2004,[23] before being reverted to NHSmail in April 2006.[24]
The Spine is a set of national services used by the NHS Care Record Service. These include:
The Spine also provides a set of security services, to ensure access to information stored on the Spine is appropriately controlled. There are, however, already suggestions these security measures are inadequate, with leaked internal memos seen by the Sunday Times mentioning "fundamental" design flaws[25]. In addition, government spokeswoman Caroline Flint failed to dispel concerns regarding access to patients' data by persons not involved in their care when she commented in March 2007 that "in general only those staff who are working as part of a team that is providing a patient with care, that is, those having a legitimate relationship with the patient, will be able to see a patient's health record."[17]
The NHS in Wales is also running a national programme for service improvement and development via the use of Information Technology - this project is called Informing Healthcare. A challenge facing both NHS CFH and Informing Healthcare is that the use of national systems previously developed by the NHS Information Authority are shared by the both these organisations and the Isle of Man. Separate provision needs to be made for devolution, while maintaining links for patients travelling across national borders.
NPfIT is currently focussed on delivering the NHS Care Record Service to GPs, Acute and Primary Hospitals, medical clinics and local hospitals and surgeries. Whilst there are no immediate plans to include opticians or dentists in the electronic care record, services are delivered to these areas of the NHS.
The programme originally divided England into five areas known as "clusters": Southern, London, East & East Midlands, North West & West Midlands, and North East. For each cluster, a different Local Service Provider (LSP) was contracted to be responsible for delivering services at a local level. This structure was intended to avoid the risk of committing to one supplier which might not then deliver; by having a number of different suppliers implementing similar systems in parallel, a degree of competition would be present which would not be if a single national contract had been tendered. However, in July 2007 Accenture withdrew from the project, and in May 2008 Fujitsu had their contract terminated, meaning that half the original contractors had dropped out of the project. As of May 2008, two IT providers were LSPs for the main body of the programme:
In the first half of 2007, David Nicholson announced the "National Programme, Local Ownership programme" (known as "NLOP") which dissolved the 5 clusters and devolved responsibility for the delivery of the programme to the ten English NHS strategic health authorities (SHAs)[27]. Connecting for Health retains responsibility for the contracts with the LSPs[28].
Under NLOP, staff employed by CfH in the Clusters had their employment transferred to the SHAs, with some being recruited to revised national CfH posts.
In addition to these LSPs the programme has appointed National Application Service Providers (NASPs) who are responsible for services that are common to all users e.g. Choose and Book and the national elements of the NHS Care Records Service that support the summary patient record and ensure patient confidentiality and information security. As of October 2005, the NASPs are:
In March 2004, EDS had their 10-year contract to supply the NHSMail service terminated.[29][30] On 1 July 2004, Cable and Wireless were contracted to provide this service, which was initially renamed Contact.[31]
IDX Systems Corporation was removed from the Southern Cluster Fujitsu Alliance in August 2005 following repeated failure to meet deadlines[26]. They were replaced in September 2005 by Cerner Corporation.
In early 2006, ComMedica's contract for supply of PACS to the North-West/West-Midlands cluster was terminated, and they were replaced by GE Healthcare.
In July 2006, the London region started the contractual replacement of IDX (which had been bought out by GE Healthcare in January 2006) as its supplier. Systems for secondary care, primary care and community and mental health services are proposed by BT to be provided by Cerner, INPS (formerly In Practice Systems) and CSE Healthcare Systems, part of the CSE-Global group of companies, respectively.[32]. This is subject to contractual negotiation known as 'CCN2'.
In September 2006, the CSC Alliance, Accenture and Connecting for Health signed a tripartite agreement that as of January 2007, the CSC Alliance would take over the responsibility for the majority of care systems the North East and Eastern clusters from Accenture, with the exception of PACS. As part of the handover process, around 300 Accenture personnel transferred under a TUPE process to CSC, and CSC took over the leases for some of Accenture's premises in Leeds. Accenture now retains only a small presence in the city for the delivery of its PACS responsibilities.
In May 2008 it was announced that following the failure to conclude renegotiation of the contract for the Southern Cluster, CfH terminated the contract with Fujitsu.[33]
The 2009 Public Accounts Committee report noted that the NPfIT had provided "little clinical functionality...to-date"
NPfIT has been criticised for inadequate attention to security and patient privacy, with the Public Accounts Committee noting "patients and doctors have understandable concerns about data security", and that the Department of Health did not have a full picture of data security across the NHS[4]. In 2000, the NHS Executive won the "Most Heinous Government Organisation" Big Brother Award from Privacy International for its plans to implement what would become the NPfIT.[34] In 2004 the NPfIT won the "Most Appalling Project" Big Brother Award because of its plans to computerise patient records without putting in place adequate privacy safeguards.[35]
The balance between the right to privacy and the right to the best quality care is a sensitive one. Also there are sanctions against those who access data inappropriately, specifically instant dismissal and loss of professional registration.
More worryingly, a January 2005 survey among doctors indicates that support for the initiative as an 'important NHS priority' has dropped to 41%, from 70% the previous year.[36] There have been concerns raised by clinicians that clinician engagement has not been addressed as much as might be expected for such a large project.
Concerns over confidentiality, and the security of medical data uploaded to the Spine have also led to opposition from civil liberties campaigners such as NO2ID the anti-database state pressure group and The Big Opt Out who provide patients with a letter to send to their doctor so that their records are withheld from the database.
As of August 5, 2005, research carried out across the NHS in England suggested that clinical staff felt that the programme was failing to engage the clinicians fully, and was at risk of becoming a white elephant. The Public Accounts Committee observed in 2009 that "the current levels of support reflect the fact that for many staff the benefits of the Programme are still theoretical"[4].
Surveys in 2008 suggested that two-thirds of doctors will refuse to have their own medical records on the system[37].
According to the Daily Telegraph, the head of NPfIT, Richard Granger, 'shifted a vast amount of the risk associated with the project to service providers, which have to demonstrate that their systems work before being paid.' The contracts meant that withdrawing from the project would leave the providers liable for 50% of the value of the contract; however, as previously mentioned, when Accenture withdrew in September 2006, Granger chose not to use these clauses, saving Accenture more than £930m[21].
The programme's largest software provider iSOFT has been seriously affected by this process and is under investigation by the UK Financial Services Authority for irregular accounting.[38] On 28 September 2006, the consultancy Accenture announced its intention to withdraw from £2bn of 10 year contracts with NPfIT, which were taken over in January 2007 by the CSC Alliance - both Accenture and CSC laid blame with iSOFT, although CSC has said it will be retaining iSOFT as its software provider for all its clusters.[39] Earlier in the year Accenture had written off $450m from its accounts because of 'significant delays' in the programme. iSOFT announced in March 2011 that trading in its shares would be suspended pending a corporate announcement. Subsequently in April 2011, the company announced that it was recommending a cash offer from CSC. CSC acquired iSOFT in August, 2011
The first trusts in the London & Southern Clusters to implement the new Cerner system found it problematic, with NHS hospital trust board minutes revealing a catalogue of errors. Difficulties with the system meant that[40]:
The NHS appointed a management team, responsible for the delivery of the system:[41]
As of 2009, overall leadership of CfH was described by the Public Accounts Committee as having been "uncertain" since the announcement that Richard Granger would be leaving the project.[4]